Question: Time (days) m b Immediate Predecessor(s) Activity a Activity a Time (days) m - 10 b 14 Immediate Predecessor(s) AE UI- Nw co N o

Time (days) m b Immediate Predecessor(s) Activity

Time (days) m b Immediate Predecessor(s) Activity a Activity a Time (days) m - 10 b 14 Immediate Predecessor(s) AE UI- Nw co N o B.D R - 14 4 16 8 18 12 Y H, I This exercise contains only parts b, c, and d. b) Activities on the critical path for the project are C-D-E-G--K. The total project completion time is 37 days. (Round your response to two decimal places.) c) For the given project, the earliest start (ES) and earliest finish (EF) are: (Round your responses to two decimal places.) Activity ESA