Question: Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several
.png)
Determine the expected completion time and variance for each activity.
Determine the total project completion time and the critical path for the project.
Determine ES, EF, LS, LF, and slack for each activity.
What is the probability that Kelle Carpet and Trim will finish the project in 40 days orless?
TIME (DAYS) IMMEDIATE b PREDECESSOR (S) ACTIVITY a4 B.D 10 14 6 12 20 10 10 14 16 HI
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
a b c The critical path is given by activities C D ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
286-B-M-L-O-M (2412).docx