Question: TIME ESTIMATE (IN DAYS) TASKS Immediate Predecessor (s) Optimistic Most Likely Pessimistic A 4 8 10 B A 2 8 24 C A 8 12

TIME ESTIMATE (IN DAYS)

TASKS

Immediate Predecessor (s)

Optimistic

Most Likely

Pessimistic

A

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E,C

6

8

20

G

E,C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D, G, H

4

6

12

K

I, J

2

2

3

  1. What is the meaning of slack time for this project?
  2. What will happen if any activity on the critical path was delayed?
  3. What is the project variance? 4
  4. What is the probability of completing this project in 41 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!