Question: TIME ESTIMATE (IN DAYS) TASKS Immediate Predecessor (s) Optimistic Most Likely Pessimistic A 4 8 10 B A 2 8 24 C A 8 12
| TIME ESTIMATE (IN DAYS) | ||||
|
TASKS |
Immediate Predecessor (s) |
Optimistic |
Most Likely |
Pessimistic |
| A |
| 4 | 8 | 10 |
| B | A | 2 | 8 | 24 |
| C | A | 8 | 12 | 16 |
| D | A | 4 | 6 | 10 |
| E | B | 1 | 2 | 3 |
| F | E,C | 6 | 8 | 20 |
| G | E,C | 2 | 3 | 4 |
| H | F | 2 | 2 | 2 |
| I | F | 6 | 6 | 6 |
| J | D, G, H | 4 | 6 | 12 |
| K | I, J | 2 | 2 | 3 |
- What is the meaning of slack time for this project?
- What will happen if any activity on the critical path was delayed?
- What is the project variance? 4
- What is the probability of completing this project in 41 days?