Question: Time Estimates ( Days ) Activity Description Predecessor ( s ) Optimistic Most Likely Pessimistic Crash Cost / Day A Bonding, insurance, tax structuring 2

Time Estimates (Days)
Activity Description Predecessor(s) Optimistic Most Likely Pessimistic Crash Cost/Day
A Bonding, insurance, tax structuring 203040 $1,500
B Foundation, concrete footings for boxes A 2065803,500
C Upgrading skybox stadium seating A 50601004,000
D Upgrading walkways, stairwells, elevators C 30501001,900
E Interior wiring, lathes B 2530359,500
F Inspection approvals E 0.10.10.10
G Plumbing D, F 2530352,500
H Painting G 1020302,000
I Hardware/AC/metal workings H 2025602,000
J Tile/carpet/windows H 810126,000
K Inspection J 0.10.10.10
L Final detail work/cleanup I, K 2025604,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!