Question: Time Estimates ( days ) Activity Optimistic Most Likely Pessimistic Immediate Predecessor ( s ) A 5 7 8 - B 6 8 1 3

Time Estimates (days)
Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s)
A 578-
B 6813-
C 246-
D 101626 A
E 91011 B
F 345 C, E
G 4810 D
H 579 F
I 91116 G, H
J 444 G