Question: Time Estimates ( days ) Activity Optimistic Most Likely Pessimistic Immediate Predecessor ( s ) A 5 7 8 - B 5 8 1 1
Time Estimates
days
Activity Optimistic Most Likely Pessimistic Immediate Predecessor
s
A
B
C
D
A
E
B
F
C
E
G
D
H
F
I
G
H
J
GThe director wants to conduct the seminar working days from now. What is the probability that everything will be ready in time? Refer to the standard normal tableLOADING.... Make sure to round all intermediate calculations for te and variance to two decimal places.
Part
The probability that the seminar will be ready in time is