Question: Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (0) m 40 50 60 31 A B C D Start a 31 44

Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (0) m 40 50 60 31 A B C D Start a 31 44 48 22 A B b 49 56 72 34 D End 5) What is the probability that this project will be completed after 110 days? A. 0.0228 B. 0.1587 C. 0.0013 D. 0.8413 E. 0.9772
 Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET)

Class Exercise \#5 5) What is the probability that this project will be completed after 110 days? A. 0.0228 B. 0.1587 C. 0.0013 D. 0.8413 E. 0.9772