Question: Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (0) m 40 50 60 31 A B C D Start a 31 44
Class Exercise \#5 5) What is the probability that this project will be completed after 110 days? A. 0.0228 B. 0.1587 C. 0.0013 D. 0.8413 E. 0.9772
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts