Question: Time Estimates (months) Most Optimistic Pessimistic Activity Probable Critical Activity? (a) (m) (b) A 3 14 17 Yes B 20 25 Yes C 3 AD

Time Estimates (months) Most Optimistic Pessimistic Activity Probable Critical Activity? (a) (m) (b) A 3 14 17 Yes B 20 25 Yes C 3 AD No D 4 10 No E 5 6 7 No F 3 13 Yes G 10 20 30 No H 7 9 11 No H 6 10 14 Yes