Question: Time Estimates ( weeks ) ActivityambActivity PredecessorA 3 5 7 - - B 4 8 1 0 AC 2 3 5 AD 6 9 1
Time Estimates weeksActivityambActivity PredecessorABACADB CED
The probability that the project could be completed in weeks or less is approximately?