Question: Using the following project information Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 3 5 none

Using the following project information

Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 2 3 5 none
B 2.3 4 5 A
C 5 7 8 A
D 3 5 7 B, C
E 4 7 14 B, C
F 2 5 8 D
G 4 5 6 E
H 6 6 8 F
I 4 8 12 G
J 2 3 3 H, I

The critical path is A-C-E-G-I-J.

Activity A B C D E F G H I J
Variance 0.25 0.20 0.25 0.44 2.78 1.00 0.11 0.11 1.78 0.03

(a) Calculate the probability that the project will be completed in 32 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 32) = enter a probability

(b) Calculate the probability that the project will be completed in 36 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 36) = enter a probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!