A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F.E is an immediate predecessor of F. The activity durations are D=4,E=3,F=8.
Select one:
A. Slack at E is 3 periods.
B. Slack at D is 3 periods.
C. The critical path is D-E-F, duration 15.
D. The critical path is D-F, duration 12.