Which of the following statements regarding CPM is true?
Select one:
A All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
B The critical path is that set of activities that has positive slack.
C All activities on the critical path have their ES equal to their LF
D Some networks have no critical path.