Question: Time left 0 : 4 4 : 5 6 Activity C has an early start time of 8 , an early finish time of 1

Time left 0:44:56
Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:
Select one:
a.0
b.1
c.4
d.5
e.9