Question: Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2
| Activity Code | Immediate Predecessors | Activity Duration (Week) |
| A | None | 3 |
| B | A | 3 |
| C | A | 2 |
| D | C | 2 |
| E | B&C | 3 |
| F | B | 2 |
| G | D&E | 1 |
| H | G | 4 |
| I | F | 7 |
| J | H&I | 2 |
| K | J | 4 |
| L | F | 6 |
| Activity Code | Early Start | Early Finish | Late start | Later Finish | Total Float |
| A | 0 | 3 | 0 | 3 | 0 |
| B | 3 | 6 | 3 | 6 | 0 |
| C | 3 | 5 | 5 | 7 | 2 |
| D | 5 | 7 | 8 | 10 | 3 |
| E | 6 | 9 | 7 | 10 | 1 |
| F | 6 | 8 | 6 | 8 | 0 |
| G | 9 | 10 | 10 | 11 | 1 |
| H | 10 | 14 | 11 | 15 | 1 |
| I | 8 | 15 | 8 | 15 | 0 |
| J | 15 | 17 | 15 | 17 | 0 |
| K | 17 | 21 | 17 | 21 | 0 |
| L | 8 | 14 | 15 | 21 | 7 |
the Critical Path is A-B-F-I-J-K=21
1-)If all critical path activities were crashed by 25%, calculate the new overall project duration?