Question: Time left 0 : 5 7 : 1 8 Figure 7 - 3 System Integration Project Consider the System Integration Project depicted in Figure 7

Time left 0:57:18
Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3. Based on the information provided, what is the expected duration of this project?
Select one:
a.15 days
b.16 days
c.17 days
d.30 days