Question: Time left 0:57:36 *For the Project network shown Compute the project durations (days) **If *Duration of Activity A = 4 days *Duration of Activity B

Time left 0:57:36 *For the Project network shown

Time left 0:57:36 *For the Project network shown Compute the project durations (days) **If *Duration of Activity A = 4 days *Duration of Activity B = 6 days *Duration of Activity C= 5 days *Duration of Activity D = 4 days *Duration of Activity E = 6 days *Duration of Activity F = 3 days *Duration of Activity G = 6 days *Duration of Activity H = 11 days *Duration of Activity I = 21 days 0 Start 0 0 0 END Compute the project durations (days)