Question: Problem 3 . ( PERT for risk management. ) Consider this project network. The following table shows a , m , b ( in days

Problem 3.(PERT for risk management.) Consider this project network.
The following table shows a,m,b(in days) for each activity of the project.
Please answer the following questions.
Compute te(expectation),(standard deviation) and V(variance) of the duration of each
activity. (Note: Keep one decimal place after the dot in your result.)
Identify the critical path by visual inspection.
(Hint: there are total 4 paths from start to end.)
The critical path(s) is:
(In case of multiple critical paths, pick one to continue.)
Compute Te(expectation) and VP(variance) of the duration of the project.
(Note: keep one decimal place after the dot in your result.)
What's the probability that the project is completed within 28 days.
For what project due date (denoted as TS) is the project to be completed on time with
95% chance?
 Problem 3.(PERT for risk management.) Consider this project network. The following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!