Question: Time Left: 09:2 Uncategorized i Question Type: MCQ Question No. 14. Mark/s: 4.00 | Negative Mark/s: 0.00 A manufacturing firm would like to develop

Time Left: 09:2 Uncategorized i Question Type: MCQ Question No. 14. Mark/s:

Time Left: 09:2 Uncategorized i Question Type: MCQ Question No. 14. Mark/s: 4.00 | Negative Mark/s: 0.00 A manufacturing firm would like to develop an aggregate plan for the next quarter. Data related to the production, demand, capacity, and cost are given below. Develop an aggregate plan by minimizing the total cost. Which of following is the minimum cost incurred to meet the aggregate plan as per demand requirements? January February March Costs Demand 700 800 600 Regular time Rs. 200 per unit Capacity Overtime Rs. 250 per unit Regular 400 450 400 Subcontract Rs. 300 per unit Overtime 200 250 200 Inventory cost Rs. 20 per unit per month Subcontracting 150 150 150 O Rs. 452500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Problem Overview You have the demand and production capacity for a manufacturing firm for the next three months January February and March Your goal i... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock