Question: Time left 1 : 1 6 : 4 5 An x - bar control chart was examined and no data points fell outside of the
Time left ::
An xbar control chart was examined and no data points fell outside of the limits Can this process be considered in control?
Select one:
a Not yet, the Rchart must be checked.
b Not yet, the number of samples must be known.
c Not yet, there could be a pattern to the points.
d Both Not yet, there could be a pattern to the points and Not yet, the chart must be checked
e Yes.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock