Question: Time left 1 : 3 7 : 4 0 Hide The statement: The project must be completed with the available resources, as no additional niring
Time left ::
Hide
The statement: "The project must be completed with the available resources, as no additional niring wilbe permitted" is an
Select one:
a Assumption
b Constraint
c Risk
d Issue