Question: Time left 1 : 3 7 : 4 0 Hide The statement: The project must be completed with the available resources, as no additional niring

Time left 1:37:40
Hide
The statement: "The project must be completed with the available resources, as no additional niring wilbe permitted" is a(n)
Select one:
a. Assumption
b. Constraint
c. Risk
d. Issue