Question: Time left 2 : 1 7 : 3 4 A scheduling system in which the last operation on a routing is scheduled first and for
Time left ::
A scheduling system in which the last operation on a routing is scheduled first and for completion on the due date is called:
a infinite scheduling
b finite scheduling
c backward scheduling
d forward scheduling