Question: Time left 2 : 1 7 : 3 4 A scheduling system in which the last operation on a routing is scheduled first and for

Time left 2:17:34
A scheduling system in which the last operation on a routing is scheduled first and for completion on the due date is called:
a. infinite scheduling
b. finite scheduling
c. backward scheduling
d. forward scheduling