Question: A scheduling system in which the last operation on a routing is scheduled first and for completion on the due date is called: finite scheduling.
A scheduling system in which the last operation on a routing is scheduled first and for completion on the due date is called:
finite scheduling.
backward scheduling.
infinite scheduling.
forward scheduling.