Question: Time (weeks) Cost ($1,000s) Activity Description Immediate Predecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6
Time (weeks) Cost ($1,000s) Activity Description Immediate Predecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 . What added project cost (in thousands of dollars) is required to meet the six-month completion time