Question: Time-Cost Trade-off Analysis Consider a Technology Prototype project with the following network and direct cost data. Normal Normal Cost Crash Time Crash Cost ID Task
Time-Cost Trade-off Analysis
Consider a Technology Prototype project with the following network and direct cost data.

Normal Normal Cost Crash Time Crash Cost ID Task Immediate Predeoessor Time (days) ($0 000] (days) ($0 000] A Identify System Reqmts 10 F5 9 101 B Develop Functional Reqmts A 6 90 6 F5 C Draft Procedure for Building Prototype A 8 105 6 155 D Design Module 1 B F F5 5 91 E Design Module 2 B 6 150 5 210 F Finalize "Build" Procedure C 4 120 1 285 (3 Develop Testing Protocol F 3 F0 1 114 H Integrate and Build Modules 1+2 Prototype D,E,F 4 90 4 135 I Test Prototype H,G 5 300 5 85