Question: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS MI b B D E F G H A B CD DE F,G 1 1 1 2 3 3 1

TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS MI b
TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS MI b B D E F G H A B CD DE F,G 1 1 1 2 3 3 1 2 3 2 2 3 4 4 4 4 5 3 3 4 11 5 6 5 What is the critical path? It is What is the expected project completion time. It will take days. Round up to FULL days i.e. 15.9 goes to 16 and 16.1 goes to 17. Word Bank: 15 days 14.67 days 15 B-E-G-H 14.67 BEGH