Question: Times (week) Times (week) Activity Cost Cost/week Normal Minimum Normal 1 $3,000 $5,000 B 2 $5,000 $3,000 $8,000 $4,000 D AC $1,000 E AC $2,000

Times (week) Times (week) Activity Cost Cost/week
Times (week) Times (week) Activity Cost Cost/week Normal Minimum Normal 1 $3,000 $5,000 B 2 $5,000 $3,000 $8,000 $4,000 D AC $1,000 E AC $2,000 4 3 $2,000 D 2 $1,000 Use the table above and we want to reduce the completion time by 1 week: For reducing the completion time by one week, which activity would result in the cheapest additional cost? OA.C. OBE OCF Activity B C OD.B Immediate Predecessor B