Question: Tips/hints for constructing the floor: The method statement states that taking two days to mix concrete with a concrete mixer on-site is not feasible. ReadyMix

Tips/hints for constructing the floor:

The method statement states that taking two days to mix concrete with a concrete mixer on-site is not feasible. ReadyMix concrete must therefore be used. Cement trucks can notionally deliver 6m3 of concrete per delivery.

Use the following productivity outputs and factors for your calculations:

Productivity outputs table

Activity

Labour

Hours

Unit

Filling excavated material into wheel barrows, wheeling and depositing less than 50m away

1 general worker

1,25

Hrs per m

Spreading and levelling, filling in 150mm

1 general worker

0,5

Hrs per m

Compacting in layers

1 general worker

2

Hrs per m

Placing of concrete, strike off and cure

1 general worker

4

Hrs per m

Allowances

Percent

Shrinkage of fill material

11 %

Wastage of fill material

5%

Wastage of ReadyMix concrete

5%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!