Question: Tips/hints for constructing the floor: The method statement states that taking two days to mix concrete with a concrete mixer on-site is not feasible. ReadyMix
Tips/hints for constructing the floor:
The method statement states that taking two days to mix concrete with a concrete mixer on-site is not feasible. ReadyMix concrete must therefore be used. Cement trucks can notionally deliver 6m3 of concrete per delivery.
Use the following productivity outputs and factors for your calculations:
| Productivity outputs table |
|
|
|
| Activity | Labour | Hours | Unit |
| Filling excavated material into wheel barrows, wheeling and depositing less than 50m away | 1 general worker | 1,25 | Hrs per m |
| Spreading and levelling, filling in 150mm | 1 general worker | 0,5 | Hrs per m |
| Compacting in layers | 1 general worker | 2 | Hrs per m |
| Placing of concrete, strike off and cure | 1 general worker | 4 | Hrs per m |
| Allowances | Percent | ||
| Shrinkage of fill material | 11 % | ||
| Wastage of fill material | 5% | ||
| Wastage of ReadyMix concrete | 5% | ||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts