Question: To assure the process will continue to achieve expected results, it's important to monitor... Critical Y's (output-process variables) that were proven to be effected by
To assure the process will continue to achieve expected results, it's important to monitor...
Critical Y's (output-process variables) that were proven to be effected by the defects.
Critical X's (in-process variables) that were proven to cause the effect.
All x's (input-process variables) that were proven to cause an effect.
Your operations Manager asked you to review the Value Stream Map and identify bottlenecks. Bottlenecks are found by
Identifying which process-step is underutilized.
Identifying the lowest level of inventory in-between steps.
identifying the process step with a cycle time equal to the Takt-time
Identifying the process step with the greatest amount of WIP (work-in-process) before it.
All Y's (output-process variables) that were proven to be effected by the defects