Question: To control the schedule, a project manager is reanalyzing the project to predict the project duration. She does this by analyzing the sequence of activities

To control the schedule, a project manager is
To control the schedule, a project manager is
To control the schedule, a project manager is reanalyzing the project to predict the project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? Flow Chart Precedence diagraming O Critical Path method O Work breakdown structure If the optimistic estimate for an activity is 12 days, and the pessimistic is 18 days, what is the PERT Standard Deviation of this activity? O1 1.3