Question: To create a computer labelled A, company BashimoX needs to combine many different parts to create A. Parts needed to combine and make the products:
To create a computer labelled "A", company BashimoX needs to combine many different parts to create A.
Parts needed to combine and make the products:
Parts B,C,D, E and F are used in creating the final product (A). To make part D it requires combining 2 parts labelled B and 2 parts labelled C. The different combinations to make the parts are listed below:
D = 2 units of B + 2 units of C
B = 1 unit of E + 2 units of F
C = 1 unit of F
E = 3 units of F
A = 3 units of B + 2 units of D + 2 units of E
Inventory on hand:
A = 0
B = 30
C = 40
D = 10
E = 25
F = 0
Production lead time:
A = 1 week
E = 1 week
F = 1 week
C = 2 weeks
D = 2 weeks
B = 3 weeks
Lot-for-lot production quantity = item C
Lot sizes for producing items:
A = multiple of 25
B = multiple of 25
D = multiple of 50
E = multiple of 50
F = multiple of 125
There is an order of 20 units of product A to be delivered in week 15
1) In excel, make the full MRP schedule for the order of product A above to determine the planned order release of all the parts. Will the company be able to make the order?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts