Question: To create a computer (their final product, named product A), company BashimoX needs to combine many different parts to create A. D = 2 units
To create a computer (their final product, named product A), company BashimoX needs to combine many different parts to create A.
D = 2 units of B + 2 units of C
B = 1 unit of E + 2 units of F
C = 1 unit of F
E = 3 units of F
A = 3 units of B + 2 units of D + 2 units of E
Inventory on hand:
A = 0
B = 30
C = 40
D = 10
E = 25
F = 0
Production lead time:
A, E and F = 1 week
C and D = 2 weeks
B = 3 weeks
Lot-for-lot production = item C
Lot sizes:
A = multiple of 25
B = multiple of 25
D = multiple of 50
E = multiple of 50
F = multiple of 125
There is an order of 20 units of product A to be delivered in week 15
In excel, make the MRP schedule for item F when the company can only use one machine and make 125 units of itemF each week. Can the company make the order? Show the changed MRP schedule for item F and any other items impacted by the change.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts