Question: to Create a network diagram Calculate paths and identify the critical path Create a table that calculates crash costs and adjusted total costs with headings:

to
Create a network diagram
Calculate paths and identify the critical path
Create a table that calculates crash costs and adjusted total costs with headings: Activity. Norm Duration, Norm Cost, Max Crash, Slope, Crash Cost, Adj Total Costs, in that order.
Identify the activity at each step that was crashed, number of crash steps, and total costs
Submit your Excel workbook to the link in this assignment by the deadline.
Activity
Preceding Activity
Normal Duration
Normal Cost
Max Crash
Crash cost/Slope
A
None
2
150
1
100
B
A
3
100
1
80
C
B
2
200
1
60
D
B
5
200
1
40
E
A
5
200
2
40
F
C
3
150
2
40
G
D
5
200
1
20
H
E, F, G
1
200
0
0
 to Create a network diagram Calculate paths and identify the critical

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!