Question: To draw a project network, we need to identify the burst activities, merge activities, and the critical path. Burst activities are activities that have multiple
To draw a project network, we need to identify the burst activities, merge activities, and the critical path.
Burst activities are activities that have multiple successors but only one predecessor. In this case, the burst activity is activity B Excavate Site
Merge activities are activities that have multiple predecessors but only one successor. In this case, there are no merge activities.
The critical path is the longest path through the network, which determines the minimum project duration. To find the critical path, we need to calculate the total duration for each path and identify the path with the longest duration.
The project network for the given information is as follows:
A B C E
D E
To find the critical path, we calculate the total duration for each path:
Path : A B C E
Total duration days
Path : A B D E
Total duration days
Therefore, the critical path is Path : A B C E with a total duration of days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock