Question: To manage a project effectively, work should be broken down into small pieces. Which of the following describes how far to decompose the work? Until
To manage a project effectively, work should be broken down into small pieces. Which of the following describes how far to decompose the work?
Until it can be estimated accurately
Until it can be realistically estimated
Until it can be completed in one day
Until it can be done by one person