Question: To track your team's progress toward completing an important project, you should useQuestion 2 1 Select one: A . a pie chart. B . a
To track your team's progress toward completing an important project, you should useQuestion Select one:
A
a pie chart.
B
a Gantt chart.
C
a pictogram.
D
an organizational chart.