Question: Tony has realized that two activities in his project cannot be done at the same time. There are simply not enough resources are available.How will

Tony has realized that two activities in his project cannot be done at the same time. There are simply not enough resources are available.How will he decide which activity should be scheduled first?Group of answer choices,The activity with the smallest duration,The activity with the highest cost,The activity with the most slack,The activity with the least slack,