Question: 2 . A project manager has realized that two activities in the project cannot be done at the same time because not enough resources are
A project manager has realized that two activities in the project cannot be done at the same time
because not enough resources are available. Activity C is critical and has a duration of days. Activity D
has days of slack and a duration of days. How should the project manager decide which actlvlty to
assign the resources first?
a The activity with the most slack.
b The activity with the least slack.
C The activity with the smallest duration.
d The activity with the largest duration.