Question: 2 . A project manager has realized that two activities in the project cannot be done at the same time because not enough resources are

2. A project manager has realized that two activities in the project cannot be done at the same time
because not enough resources are available. Activity C is critical and has a duration of 5 days. Activity D
has 2 days of slack and a duration of 3 days. How should the project manager decide which actlvlty to
assign the resources first?
a. The activity with the most slack.
b. The activity with the least slack.
C. The activity with the smallest duration.
d. The activity with the largest duration.