Question: Top - down estimates can be used for the following: a . Calculate the availability of resources b . Feasibility Studies c . Evaluating the

Top-down estimates can be used for the following:
a. Calculate the availability of resources
b. Feasibility Studies
c. Evaluating the expertise of the team members
d. Evaluating the project deliverables
 Top-down estimates can be used for the following: a. Calculate the