Question: Topic: Network Optimization Problem 1. CONSTRUCT ACTIVITY NETWORK b) DETERMINE THE SHORTEST ROUTE C) MAXIMUM FLOW. BEGINNING ENDING ACTIVITY TIME EVENT EVENT (WEEKS) 1 2

Topic: Network Optimization Problem

1. CONSTRUCT ACTIVITY NETWORK b) DETERMINE THE SHORTEST ROUTE C) MAXIMUM FLOW.

BEGINNING ENDING ACTIVITY TIME

EVENT EVENT (WEEKS)

1 2 4

1 3 5

1 4 6

2 5 8

3 5 5

3 6 6

4 6 7

5 7 9

6 7 7