Question: toring Enabled: Second Midterm Exam i Soved Help Save & Exit 7 A project leader has realized that two activities in the project cannot be
toring Enabled: Second Midterm Exam i
Soved
Help
Save & Exit
A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity is critical and has a duration of days. Activity has days of slack and a duration of days. How will the project leader decide which activity should be scheduled first?
Multiple Choice
The activity with the smallest duration
The activity with the least slack
The activity with the most slack
t
The activity with the lowest identification number
The activity with the highest cost
Prev