Question: Total slack ( float) can be calculated only after doing on project network diagram Select one: a. Backward Pass b. Forward Pass O c. Critical

Total slack ( float) can be calculated only after
Total slack ( float) can be calculated only after doing on project network diagram Select one: a. Backward Pass b. Forward Pass O c. Critical path O d. Both Forward Pass and Backward pass