Question: Use the three - step process below, calculate a schedule with ES , EF , LS , LF dates for project network diagram shown below,
Use the threestep process below, calculate a schedule with ES EF LS LF dates for project network diagram shown below, as well as identify critical path and its length.
Forward pass: determine ES EF
Backward pass: determine LS LF
Calculate floatslack & identify critical path
Float LS ES
Assumptions
The ES date of the first task is on the first day of the project
Legend
The duration of tasks is counted in days.
The start of a day is assumed to be am and the finish is pm
The project finish date is the EF of the last taskext
Note: The boxes in the figure below are fillable. You can type in your answers directly.
The critical path is list tasks on the critical path: qquad ; length of the critical path is qquad days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock