Question: Use the three - step process below, calculate a schedule with ES , EF , LS , LF dates for project network diagram shown below,

Use the three-step process below, calculate a schedule with ES, EF, LS, LF dates for project network diagram shown below, as well as identify critical path and its length.
1. Forward pass: determine ES, EF
2. Backward pass: determine LS, LF
3. Calculate float/slack \& identify critical path
- Float \(=\) LS - ES
Assumptions
- The ES date of the first task is on the first day of the project
Legend
- The duration of tasks is counted in days.
- The start of a day is assumed to be 8 a.m. and the finish is 5 p.m.
- The project finish date is the EF of the last taskext
Note: The boxes in the figure below are fillable. You can type in your answers directly.
The critical path is (list tasks on the critical path): \(\qquad \) ; length of the critical path is \(\qquad \) days.
 Use the three-step process below, calculate a schedule with ES, EF,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!