Question: 10. In the NPV calculation if you change all variables at the same time to do robustness checks on your original base estimates, then that

 10. In the NPV calculation if you change all variables at

10. In the NPV calculation if you change all variables at the same time to do robustness checks on your original base estimates, then that is called A) Sensitivity analyses B) Scenario analyses OC) Value at risk (VAR) analyses OD) Average accounting return analyses E) Internal rate of return analyses