Question: CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $395,000 is estimated to result in
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $395,000 is estimated to result in $144,000 in annual pretax cost savings. The press qualifies for 100 percent bonus depreciation, and it will have a salvage value at the end of the project of $45,000. The press also requires an initial investment in spare parts inventory of $15,000, along with an additional $2,000 in inventory for each succeeding year of the project. The shop's tax rate is 22 percent and its discount rate is 11 percent. What is the project's NPV? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) Net present value