Question: Job 731 was recently completed. The following data have been recorded on its job cost sheet: The company applies manufacturing overhead on the basis of
Job 731 was recently completed. The following data have been recorded on its job cost sheet: The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 731 would be: 5094 4254 2418 3288