Question: Question 24 Job C250 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $3,193 Direct labor-hours 21 labor

Question 24 Job C250 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $3,193 Direct labor-hours 21 labor hours Direct labor wage rate $12 per labor hour Machine-hours 166 machine hours The Company applies manufacturing overhead on the basis of machine- hours. The predetermined overhead rate is $15 per machine-hour. The total cost that would be recorded on the job cost sheet for Job C250 would be: $3,760 $5.935 $3,220 O $3,445