Question: The ETC for the remaining work =10,000 USD The actual cost spent so far=8000 USD The budget at completion =15,000 USD The variance at completion

 The ETC for the remaining work =10,000 USD The actual cost

The ETC for the remaining work =10,000 USD The actual cost spent so far=8000 USD The budget at completion =15,000 USD The variance at completion is: .2000 USD 3000 USD 18000 USD -3000 USD