Question: The ETC for the remaining work = 1 0 , 0 0 0 USD The actual cost spent so far = 8 0 0 0

The ETC for the remaining work =10,000 USD
The actual cost spent so far =8000 USD
The budget at completion =15,000 USD
The variance at completion is: