Question: The performance report for Zhang Industries includes the following van Flexible Budget Price Quantity Direct Materials $25,500 55.000 27 Direct Labor $10,000 22 37.500 Variable

The performance report for Zhang Industries includes the following van Flexible Budget Price Quantity Direct Materials $25,500 55.000 27 Direct Labor $10,000 22 37.500 Variable Overhead $14 200 F 516,700 F $2.500 U Some items are missing. Based on the other information provided what is the direct laborate var? OA 2,500 U B. 17,500 F C 7.500 F OD Information on the standard and actual direct labor rates is needed to solve the