Question: WORKERS BUDGET (RM) Activity precedence Duration (day) A 2 B A 6 2 500 600 2 A 4. 2 400 D A 2 1 1000

WORKERS BUDGET (RM) Activity precedence Duration (day) A 2 B A 6 2 500 600 2 A 4. 2 400 D A 2 1 1000 1200 E 2 1 F 4 1 200 G B,D,E,F 2 1 200 You need to make a report to your manager based on below: 1. Draw a Gantt chart and resource histogram based on the table given. 2. There is a resource constraint. Calculate the duration of project where you have to minimize and smooth the number of workers if the workers available are only 2 per day. Use a Resource-Constrained method and show your answer step by step. 3. Draw the budget baseline for the project. Assume that all the budget (except for activity E) is equally divided to the activity duration. The budget for activity E is released at the end of the activity duration 4. Splitting of activity is not allowed. WORKERS BUDGET (RM) Activity precedence Duration (day) A 2 B A 6 2 500 600 2 A 4. 2 400 D A 2 1 1000 1200 E 2 1 F 4 1 200 G B,D,E,F 2 1 200 You need to make a report to your manager based on below: 1. Draw a Gantt chart and resource histogram based on the table given. 2. There is a resource constraint. Calculate the duration of project where you have to minimize and smooth the number of workers if the workers available are only 2 per day. Use a Resource-Constrained method and show your answer step by step. 3. Draw the budget baseline for the project. Assume that all the budget (except for activity E) is equally divided to the activity duration. The budget for activity E is released at the end of the activity duration 4. Splitting of activity is not allowed
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts